District | No of ULBs | Total no of enterprises to be formed in 2017-18 | Progress during the week (4th week of January) | No of units started | Date of starting | Production of the unit during the week(4th week of January) | Total Production of the unit (in bottles) | Turnover of the unit during the week (Rs) | Total turnover of the unit (Rs) |
Thiruvananthapuram | 5 | 3 | Beneficiary Selection completed. Meeting with agency & council completed | ||||||
Kollam | 5 | 2 | |||||||
Pathanamthitta | 4 | 0 | |||||||
Alappuzha | 6 | 2 | Beneficiary Selection completed | ||||||
Kottayam | 6 | 0 | |||||||
Idukki | 2 | 0 | |||||||
Ernakulam | 14 | 3 | Beneficiary Selection completed | ||||||
Thrissur | 8 | 1 | Beneficiary Selection completed | ||||||
Palakkad | 7 | 0 | |||||||
Malappuram | 12 | 3 | Beneficiary Selection completed | ||||||
Kozhikode | 8 | 1 | Beneficiary Selection completed | ||||||
Wayanad | 3 | 2 | Beneficiary Selection completed | ||||||
Kannur | 10 | 0 | |||||||
Kasaragod | 3 | 0 | |||||||
Total | 93 | 17 |
ULB name | Manager in charge | Total no. of units to be formed | Progress during the week (4th week of January) | No of units started | Date of starting | Production of the unit during the week (4th week of January) | Total Production of the unit (in bottles) | Turnover of the unit during the week (Rs) | Total turnover of the unit (Rs) |
Thiruvananthapuram | Abik Nirmal Dev | 1 | 3 persons identified | ||||||
Neyyatinkara | Shamkrishna.B | 1 | 4 persons identified | ||||||
Varkala | Abik Nirmal Dev | 1 | |||||||
Kollam | Manu. M | 1 | 6 persons identified | ||||||
Kottarakkara | Deepa Prabhakar | 1 | |||||||
Alappuzha | Sunu John | 1 | 5 persons identified | ||||||
Mavelikkara | Prithvi Raj | 1 | |||||||
Kalamassery | Neena John | 1 | 3 persons identified | ||||||
Muvattupuzha | Neena John | 1 | |||||||
Thrippunithura | Radhika Ramakrishnan | 1 | |||||||
Chalakudy | Lipson.P | 1 | |||||||
Ponnani | Renjith Alex | 1 | |||||||
Tirur | Mujeeb Ur Rehman | 1 | 5 persons identified | ||||||
Parappanangadi | Vipitha | 1 | 5 persons identified | ||||||
Mukkom | Bavith | 1 | |||||||
Kalpetta | Nisha.S | 1 | 1 person identified | ||||||
Sulthan Bathery | Shymon Devassia | 1 | 5 persons identified | ||||||
Total | 17 |
District | No of ULBs | Total no of enterprises to be formed in 2017-18 | Progress during the week(4th week of January) | No of units started | Date of starting | Turnover of the unit during the week (Rs) | Total turnover of the unit (Rs) |
Thiruvananthapuram | 5 | 1 | |||||
Kollam | 5 | 2 | |||||
Pathanamthitta | 4 | 0 | |||||
Alappuzha | 6 | 1 | |||||
Kottayam | 6 | 0 | |||||
Idukki | 2 | 1 | Beneficiary Selection completed | ||||
Ernakulam | 14 | 4 | Beneficiary Selection completed | ||||
Thrissur | 8 | 1 | |||||
Palakkad | 7 | 0 | |||||
Malappuram | 12 | 3 | |||||
Kozhikode | 8 | 5 | |||||
Wayanad | 3 | 1 | Beneficiary Selection completed | ||||
Kannur | 10 | 0 | |||||
Kasaragod | 3 | 0 | |||||
Total | 93 | 19 |
ULB name | Manager in charge | Total no. of units to be formed | Progress during the week (4th week of January) | No of units started | Date of starting | Turnover of the unit during the week (Rs) | Total turnover of the unit (Rs) |
Thiruvananthapuram | Abik Nirmal Dev | 1 | |||||
Karunagappally | Deepa Prabhakar | 1 | |||||
Kottarakkara | Deepa Prabhakar | 1 | |||||
Mavelikkara | Prithvi Raj | 1 | |||||
Kattappana | Johny Joseph | 1 | 5 persons identified. Project submitted to bank. | ||||
Kalamassery | Neena John | 1 | 4 persons identified. Project submitted to bank. | ||||
Thrippunithura | Neena John | 1 | 3 persons identified. Project submitted to bank. | ||||
Kochi | Mobeesh Muraleedharan | 2 | 5 persons identified | ||||
Chavakkad | Lipson.P | 1 | |||||
Tirur | Mujeeb Ur Rehman | 3 | |||||
Koyilandi | Ramya.P.M | 1 | |||||
Payyoli | 1 | ||||||
Koduvally | Mujeeb Ur Rehman | 3 | |||||
Kalpetta | Nisha.S | 1 | |||||
Total | 19 |
District | No of ULBs | Total no of enterprises to be formed in 2017-18 | Progress during the week (4th week of January) | No. of units started | Date of starting | No of customers served (4th week of January) | Total no of customers served by the unit | Turnover of the unit during the week (Rs) | Total turnover of the unit (Rs) |
Thiruvananthapuram | 5 | 1 | |||||||
Kollam | 5 | 1 | |||||||
Pathanamthitta | 4 | 1 | Beneficiary Selection completed | ||||||
Alappuzha | 6 | 0 | |||||||
Kottayam | 6 | 1 | Beneficiary Selection completed | ||||||
Idukki | 2 | 1 | Beneficiary Selection completed | ||||||
Ernakulam | 14 | 7 | Beneficiary Selection completed in 2 ULBs | ||||||
Thrissur | 8 | 1 | Beneficiary Selection completed | ||||||
Palakkad | 7 | 0 | |||||||
Malappuram | 12 | 2 | Beneficiary Selection completed in 1 ULB | ||||||
Kozhikode | 8 | 2 | Beneficiary Selection completed | ||||||
Wayanad | 3 | 0 | |||||||
Kannur | 10 | 0 | |||||||
Kasaragod | 3 | 0 | |||||||
Total | 93 | 17 |
ULB name | Manager in charge | Total no. of units to be formed | Progress during the week(4th week of January) | No of units started | Date of starting | No of customers served (4th week of January) | Total no of customers served by the unit | Turnover of the unit during the week (Rs) | Total turnover of the unit (Rs) |
Thiruvananthapuram | Abik Nirmal Dev | 1 | |||||||
Kottarakkara | Deepa Prabhakar | 1 | |||||||
Thiruvalla | Ajith Kumar | 1 | 20 persons identified | ||||||
Kottayam | Binu George | 1 | 5 persons identified | ||||||
Kattappana | Johny Joseph | 1 | 5 persons identified | ||||||
Maradu | 1 | ||||||||
Perumbavoor | 1 | ||||||||
Koothattukulam | Mobeesh Muraleedharan | 1 | |||||||
Piravom | Mobeesh Muraleedharan | 1 | |||||||
North Paravoor | Babitha Jose | 1 | 5 persons identified | ||||||
Kochi | Mobeesh Muraleedharan | 2 | 5 persons identified | ||||||
Guruvayoor | Lakshmi Priyadarshini | 1 | |||||||
Malappuram | Subair Ul Avan | 1 | 6 persons identified | ||||||
Tirur | Mujeeb Ur Rehman | 1 | 5 persons identified | ||||||
Payyoli | 1 | ||||||||
Feroke | Bhavith | 1 | |||||||
Total | 17 |