PAYYANNUR MUNCIPALITY
Ensure to address all homeless with land from Payyannur muncipality through beneficiary led construction of
Pradhan Manthri Awas Yojana Scheme(PMAY). total of 623 beneficiaries are included in the scheme through five dprs. After data cleaning 75 beneficiaries are under the process of exclusion from the scheme because of ineligibility. Council passed the resolution for this exclusion.
19 eligible beneficiaries from LIFE list are included in PMAY scheme.
Status of Implementation through DPR wise are shown below
DPR | Total no. of beneficiaries | Actual no. after cleaning | Total no. enrolled | Got permitt | Agreement executed | Relased 1 instalment | 2 instalment | 3 instalment | completed |
1 | 247 | 221 | 221 | 215 | 215 | 214 | 209 | 140 | 40 |
2 | 163 | 146 | 146 | 125 | 115 | 113 | 78 | 15 | 0 |
3 | 141 | 118 | 118 | 110 | 108 | 100 | 66 | 13 | 0 |
4 | 12 | 9 | 9 | 8 | 6 | 6 | 0 | 0 | 0 |
5 | 60 | 54 | 54 | 50 | 40 | 35 | 0 | 0 | 0 |
List of beneficiaries attached to MIS and geotagged are shown below
DPR no. | Total no. of beneficiaries | No. of beneficiaries attached to MIS | No. houses geotagged | No. of points geotagged |
1 | 247 | 247 | 201 | 373 |
2 | 163 | 160 | 95 | 151 |
3 | 141 | 138 | 85 | 132 |
4 | 12 | 9 | 5 | 7 |
5 | 60 | 58 | 33 | 42 |
Total | 623 | 612 | 419 | 705 |
- Submitted housing for all plan of action(HFAPoA)
-Data cleaning completed and taken counsil resolution
-Land identified for LIFE/ AHP
-CLSS 54 beneficiaries and 9 are sanctioned.
-Convergence with ayyankali for construction and well recharge for PMAY beneficiaries
-Ring compost for all PMAY beneficiries
3 persons are sensitized and atteneded orientatation for skill training under NULM.
Process are going for agreement execution of all eligible beneficiaries before 30th of July 2018
100% of adhar seeding and geotagging by August 15
- Beneficiary meets organised at ward level and village level for sppeedy implementation
-Inter departmental meeting
-Muncipal level beneficiary meet for constrain solving
-Kudumbasree construction unit establishment ongoing