PMAY Status
Cherpulassery Municipality has taken demand survey for assessing the actual demand of housing. In order to initiate the demand survey ULB has collected and prepared a probability list of beneficiaries in each ward through counsellors and Kudumbashree members. Based on this list Secretary has appointed one enumerator for each ward to collect the housing demand of each potential beneficiary. Training for these enumerators, counsellors and ULB officials was conducted at ULB level. Data entry of these demand survey forms has done by Kudumbashree unit in excel sheet and also in Central Govt. MIS
Total Pmay
BLC- N 474
Current Status of PMAY
DPR |
Instalment 1 |
Instalment 2
|
Instalment 3
|
Instalment 4
|
I - 100 |
100 |
96 |
95 |
42 |
II- 374 |
0 |
0 |
0 |